Replies: 1 comment 4 replies
-
No, normally it's not right that a MO switches status from approved to confirmed.
Note that the replanning capabilities are far more advanced on the Enterprise Edition. An example to illustrate: In the Enterprise Edition, an approved MO that wasn't completed on time will automatically be moved forward to a new date in the future. This move is then also propagated to other approved MO that need the material produced by the first MO, and the complete chain of MOs is moved to new dates where they are material and capacity feasible. Another example: When supplier delays his promised delivery of a PO, the Enterprise Edition will move the complete chain of approved MO that depend on the supplier's delivery. The Community Edition doesn't do that propagation either. |
Beta Was this translation helpful? Give feedback.
-
Happy new year to anyone reading!
Today I'm here to ask about confirmation about one behavior I detected and not found documented, so I don't know if it's done on purpose a behavior, something to improve, or if I need to activate some flag or if I'm missing something.
I have a MO which was not done in the planned time (planned for today and the worker could not start this task), so I've populated a manufacturing order on approved status, at start=tomorrow 1am. (in order to try to create some replan for tomorrow).
Note my calendar of all my resources is only from 9am to 5pm.
The result after the planning is a confirmed order. When I was expecting some planning as the statement "The manufacturing order is present in the ERP system but can still be rescheduled by frePPLe (optimization input).".
I also checked that if the date for this MO is on calendar-available hours it keeps the MO as it is.
So it's normal that frepple confirms something I said that it's still on approved?
Should I be doing something different to replan a MO?
Beta Was this translation helpful? Give feedback.
All reactions