Step 7 in Data loading wizard for production planning #533
Unanswered
atistabiur
asked this question in
Q&A
Replies: 1 comment 1 reply
-
Step 5 and 6 are locked as long as you don't have manufacturing order or purchase order yet. Which is indeed too strict. As a workaround, go to the screen "purchasing/purchase orders" and create a record there in the status "proposed". That will unlock the steps and allow you to go forward. |
Beta Was this translation helpful? Give feedback.
1 reply
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
Program is no allowing to checkbox 5 and 6 in spite i have already completed these tasks.
What is preventing to got to step 7 after completing all the steps before ??
Beta Was this translation helpful? Give feedback.
All reactions