Replies: 1 comment
-
The Community Edition doesn't have the capability to reschedule approved manufacturing orders. Only the Enterprise and Cloud Editions will reschedule approved orders. When approved orders are not feasible (i.e. planned in the past, missing material or overloading capacity) the algorithm will move approved to a new date where they are feasible.
Buy the Enterprise or Cloud Edition :-) |
Beta Was this translation helpful? Give feedback.
0 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
I had a purchase order and a production order. Bost had the status "approved".
Now the documentation say: The manufacturing order is present in the ERP system but can still be rescheduled by frePPLe (optimization input).
The planing engine dont rescheduled these orders.
What can I do?
Can you help me
There is enough capacity
Beta Was this translation helpful? Give feedback.