When we generate a plan, we plan for the complete horizon in which we see demand. The "resource report" will show a resource loading for that period (plus a small extra).

If you have demand for the next 5 years, you will see a resource load for the next 5 years and a bit.
If you have demand for the next 1 months, you will see a resource load for the next 1 month and a bit only.