When I execute a plan with the option of capacity limet my resources had only capacity for the next month. |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments 1 reply
-
When we generate a plan, we plan for the complete horizon in which we see demand. The "resource report" will show a resource loading for that period (plus a small extra). If you have demand for the next 5 years, you will see a resource load for the next 5 years and a bit. |
Beta Was this translation helpful? Give feedback.
-
Yes, what I described fully applies. In this case there is something wrong on your model and both of you demands are not being planned (see the red cells in your first screenshot). Since there is no activity at all on the resource we only export the 1 month in the future. |
Beta Was this translation helpful? Give feedback.
When we generate a plan, we plan for the complete horizon in which we see demand. The "resource report" will show a resource loading for that period (plus a small extra).
If you have demand for the next 5 years, you will see a resource load for the next 5 years and a bit.
If you have demand for the next 1 months, you will see a resource load for the next 1 month and a bit only.